PSE has a 50% ownership interest in Colstrip Units 1 and 2 and a 25% interest in Colstrip Units 3 and 4. In March 2013, the Sierra Club and the Montana Environmental Information Center filed a Clean Air Act citizen suit against all Colstrip owners in the U.S. District Court, District of Montana. In July 2016, PSE reached a settlement with the Sierra Club to dismiss all of the Clean Air Act allegations against the Colstrip Generating Station, which was approved by the court in September 2016. As part of the settlement that was signed by all Colstrip owners, Colstrip 1 and 2 owners, PSE and Talen Energy, agreed to retire the two oldest units (Units 1 and 2) at Colstrip in eastern Montana no later than July 1, 2022. Depreciation rates were updated in the GRC effective December 19, 2017, where PSE's depreciation increased for Colstrip Units 1 and 2 to recover plant costs to the expected shutdown date. Additionally, PSE has accelerated the depreciation of Colstrip Units 3 and 4, per the terms of the GRC settlement, to December 31, 2027. The GRC also repurposed PTCs and hydro-related treasury grants to recover unrecovered plant costs and to fund and recover decommissioning and remediation costs for Colstrip Units 1 through 4.

On June 11, 2019, Talen made a public announcement that Colstrip 1 and 2 will be shut down at the end of the year due to operational losses associated with the Units. The regulatory asset associated with early retirement of Colstrip Units 1 and 2 increased from $130.7 million as of December 31, 2018 to $178.2 million as of June 30, 2019. The Washington Clean Energy Transition Act requires the WUTC to provide recovery of the investment, decommissioning, and remediation costs associated with the facilities that are not recovered through the repurposed PTC's and hydro-related treasury grants. The full scope of decommissioning activities and costs may vary from the estimates that are available at this time.

PSE filed a general rate case (GRC) with the Washington Commission on June 20, 2019 requesting an overall increase in electric and natural gas rates of 6.9% and 7.9% respectively. PSE requested a return on equity of 9.8 percent with an overall rate of return of 7.62 percent. In addition to the traditional areas of focus (revenue requirements, cost allocation, rate design and cost of capital), the company included an attrition adjustment mechanism to address the expected regulatory lag in the rate year. Additionally, as the non-plant related excess deferred taxes that resulted from the Tax Cuts and Jobs Act (TCJA) remained outstanding from PSE’s Expedited Rate Filing (ERF) as discussed below, PSE requested in its general rate case to pass back the amounts over four years. PSE awaits suspension of the filing and for the Commission to set a procedural calendar.

In May 2019, Washington State passed the 100 Percent Clean Electric Bill that supports Washington's clean energy economy and transitioning to a clean, affordable, and reliable energy future. The Clean Energy Transition Act requires all electric utilities to eliminate coal-fired generation from their allocation of electricity by December 31, 2025; to be carbon-neutral by January 1, 2030, through a combination of non-emitting electric generation, renewable generation, and/or alternative compliance options; and makes it the state policy that, by 2045, 100% of electric generation and retail electricity sales will come from renewable or non-emitting resources. Clean Energy Implementation plans are required every four years from each investor-owned utility (IOU) and must propose interim targets for meeting the 2045 standard between 2030 and 2045, and lay out an actionable plan that they intend to pursue to meet the standard. The WUTC may approve, reject, or recommend alterations to an IOU’s plan.
In order to meet these requirements, the Act clarifies WUTC’s authority to consider and implement performance and incentive-based regulation, multi-year rate plans, and other flexible regulatory mechanisms where appropriate. The Act mandates that the Commission accelerate depreciation schedules for coal-fired resources, including transmission lines, to December 31, 2025, or to allow investor-owned utilities to recover costs in rates for earlier closure of those facilities. Investor-owned utilities will be allowed to earn a rate of return on certain Power Purchase Agreements (PPA's) and 36 months deferred accounting treatment for clean energy projects (including PPAs) identified in the utility’s clean energy implementation plan.

IOUs are considered to be in compliance when the cost of meeting the standard or an interim target within the four-year period between plans equals a 2% increase in the weather adjusted sales revenue to customers from the previous year. If relying on the cost cap exemption, IOUs must demonstrate that they have maximized investments in renewable resources and non-emitting generation prior to using alternative compliance measures.